Labour for plubing works - Can you do this over next few days? Plan at end if you scoll down.

Today / Tomorrow

1. Extend exiting hot and cold supply by 8 metres - No chasing needed anymore
2. Adjust Radiator Outlet in Concrete Screed

Wednesday / Thursday

1.  Surface Mount  10 metres of copper pipe (section to kitchen sink across wall)
2. Install 8 metres of surface mount 40mm wastepipe with 4 swept bends and rodding access by new kitchen sink. See blue on diagram
3. Convert 40mm to 50mm wastepipe where appliances attach
Connect Appliances to Waste
4. Install tap and connect to hot and cold supply

Cap off old hot and cold water supply to existing kitchen in the utility cupboard

Chase / cut new 4 metre Channel in one breezeblock Wall for hot and cold supply. Cuboards will be moved for you to chase.

Install 2 * 10 metres of 15mm pipe for hot and cold supply to new kitchen sink from supply in utility cupboard. 

Finish with isolation valves with junction for new sink and dishwasher to connect to cold supply. 


Waste Pipe

Install 8 metres of 40mm Wastepipe along 3 walls with . Revew Plans

Waste Pipe will finish in gully


After units installed and worktop sealed. Come back and connect trap to sink. Connect trap to waste pipe and attached dishwasher and washing machine. 

Install kitchen tap and attached to hot and cold water supply and install washing machine and dishwaser.
Proposed Plan